Ghost incremental backups unscheduled?

louise

Distinguished
Jan 24, 2003
343
0
18,780
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

I've just purchased Ghost 9. My plan was to do a full image
periodically and in between, do incremental backups - to a USB hard
drive. Running Win XP Pro.

The full image is working fine.

I want to be able to do incremental backups when I want to - when I'm
not using my computer - NOT on a schedule because my usage times are
erratic and a scheduled backup, no matter when I set it for, will
interrupt me - I want to do manual incremental backups every day.

I've searched the help files and it looks to me like I can do a manual
image when I want to, but incrementals have to be scheduled. Is there
any way around this or have I missed something?

TIA

Louise
 
G

Guest

Guest
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

Just yesterday, I gave up on Ghost 9. Too buggy for my taste. Others
have made similar comments. Perhaps with work it will function
consistently, but why put so much work into it when Drive Image 2002
and Ghost 2003 work so well. I installed Ghost 9 onto a fairly new
install of XP SP2, and it hangs, crashes, and fails to liveupdate. So,
I'm giving up for now, and going back to the tried and true by putting
DI 2002 back on.

I have Drive Image 7 laying around, maybe it will work better even
though Ghost 9 and DI 7 are similar programs.

Irwin

Louise wrote:
> In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com
says...
> >
> > "Louise" <none@nospam.com> wrote in message
> > news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
> > > I've just purchased Ghost 9. My plan was to do a full image
> > > periodically and in between, do incremental backups - to a USB
hard
> > > drive. Running Win XP Pro.
> > >
> > > The full image is working fine.
> > >
> > > I want to be able to do incremental backups when I want to - when
I'm
> > > not using my computer - NOT on a schedule because my usage times
are
> > > erratic and a scheduled backup, no matter when I set it for, will
> > > interrupt me - I want to do manual incremental backups every day.
> > >
> > > I've searched the help files and it looks to me like I can do a
manual
> > > image when I want to, but incrementals have to be scheduled.
> >
> > No they dont, its just poor documentation.
> >
> > Just set it up as you are told to and it should be obvious how to
> > do the incremental backups manually once you have done that.
> >
> > Once you have setup the backup job, in the advanced view,
> > just select the Backup Jobs tab and see that job listed as
> > unsheduled. There will be a 'run job now' entry in the
> > Backup Job Tasks list on the left when you have the job selected.
> >
> > > Is there any way around this
> >
> > Yep, its trivial to do in practice.
> >
> > > or have I missed something?
> >
> > The documentation has basically.
> >
> >
> >
> Ghost seems to "know" that when I hit the run backup option, it will
do
> an incremental backup. How does it know when it's time to do another
> full image?
>
> Thanks.
>
> Louise
 

Sam

Distinguished
Mar 30, 2004
866
0
18,980
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

Don't know if your problem with XP SP2 was because of the following, but
will quote part of the applicable Ghost document just in case. Sam

Document ID:2004101410380862
Last Modified:12/20/2004


Norton Ghost 9.0 compatibility with Windows XP Service Pack 2
Situation:
You need to know if Norton Ghost 9.0 is compatible with Windows XP Service
Pack 2.

Solution:
Norton Ghost 9.0 is compatible with Windows XP Service Pack 2. However, you
need to modify the Data Execution Prevention (DEP) policy to allow Norton
Ghost 9.0 to launch its services during startup.

If you have already installed Ghost 9.0 and Windows XP Service Pack 2, see
the document Blue screen error after installing Norton Ghost 9.0 or Windows
XP Service Pack 2






"Irwin" <ebct@hotmail.com> wrote in message
news:1105481451.932965.321610@f14g2000cwb.googlegroups.com...
> Just yesterday, I gave up on Ghost 9. Too buggy for my taste. Others
> have made similar comments. Perhaps with work it will function
> consistently, but why put so much work into it when Drive Image 2002
> and Ghost 2003 work so well. I installed Ghost 9 onto a fairly new
> install of XP SP2, and it hangs, crashes, and fails to liveupdate. So,
> I'm giving up for now, and going back to the tried and true by putting
> DI 2002 back on.
>
> I have Drive Image 7 laying around, maybe it will work better even
> though Ghost 9 and DI 7 are similar programs.
>
> Irwin
>
> Louise wrote:
>> In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com
> says...
>> >
>> > "Louise" <none@nospam.com> wrote in message
>> > news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
>> > > I've just purchased Ghost 9. My plan was to do a full image
>> > > periodically and in between, do incremental backups - to a USB
> hard
>> > > drive. Running Win XP Pro.
>> > >
>> > > The full image is working fine.
>> > >
>> > > I want to be able to do incremental backups when I want to - when
> I'm
>> > > not using my computer - NOT on a schedule because my usage times
> are
>> > > erratic and a scheduled backup, no matter when I set it for, will
>> > > interrupt me - I want to do manual incremental backups every day.
>> > >
>> > > I've searched the help files and it looks to me like I can do a
> manual
>> > > image when I want to, but incrementals have to be scheduled.
>> >
>> > No they dont, its just poor documentation.
>> >
>> > Just set it up as you are told to and it should be obvious how to
>> > do the incremental backups manually once you have done that.
>> >
>> > Once you have setup the backup job, in the advanced view,
>> > just select the Backup Jobs tab and see that job listed as
>> > unsheduled. There will be a 'run job now' entry in the
>> > Backup Job Tasks list on the left when you have the job selected.
>> >
>> > > Is there any way around this
>> >
>> > Yep, its trivial to do in practice.
>> >
>> > > or have I missed something?
>> >
>> > The documentation has basically.
>> >
>> >
>> >
>> Ghost seems to "know" that when I hit the run backup option, it will
> do
>> an incremental backup. How does it know when it's time to do another
>> full image?
>>
>> Thanks.
>>
>> Louise
>
 
G

Guest

Guest
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

"Louise" <none@nospam.com> wrote in message
news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
> I've just purchased Ghost 9. My plan was to do a full image
> periodically and in between, do incremental backups - to a USB hard
> drive. Running Win XP Pro.
>
> The full image is working fine.
>
> I want to be able to do incremental backups when I want to - when I'm
> not using my computer - NOT on a schedule because my usage times are
> erratic and a scheduled backup, no matter when I set it for, will
> interrupt me - I want to do manual incremental backups every day.
>
> I've searched the help files and it looks to me like I can do a manual
> image when I want to, but incrementals have to be scheduled.

No they dont, its just poor documentation.

Just set it up as you are told to and it should be obvious how to
do the incremental backups manually once you have done that.

Once you have setup the backup job, in the advanced view,
just select the Backup Jobs tab and see that job listed as
unsheduled. There will be a 'run job now' entry in the
Backup Job Tasks list on the left when you have the job selected.

> Is there any way around this

Yep, its trivial to do in practice.

> or have I missed something?

The documentation has basically.
 

louise

Distinguished
Jan 24, 2003
343
0
18,780
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com says...
>
> "Louise" <none@nospam.com> wrote in message
> news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
> > I've just purchased Ghost 9. My plan was to do a full image
> > periodically and in between, do incremental backups - to a USB hard
> > drive. Running Win XP Pro.
> >
> > The full image is working fine.
> >
> > I want to be able to do incremental backups when I want to - when I'm
> > not using my computer - NOT on a schedule because my usage times are
> > erratic and a scheduled backup, no matter when I set it for, will
> > interrupt me - I want to do manual incremental backups every day.
> >
> > I've searched the help files and it looks to me like I can do a manual
> > image when I want to, but incrementals have to be scheduled.
>
> No they dont, its just poor documentation.
>
> Just set it up as you are told to and it should be obvious how to
> do the incremental backups manually once you have done that.
>
> Once you have setup the backup job, in the advanced view,
> just select the Backup Jobs tab and see that job listed as
> unsheduled. There will be a 'run job now' entry in the
> Backup Job Tasks list on the left when you have the job selected.
>
> > Is there any way around this
>
> Yep, its trivial to do in practice.
>
> > or have I missed something?
>
> The documentation has basically.
>
>
>
Thank you so much. Yes, it's obviously right there and the
docomentation is TERRIBLE. You've solved my dilemma and my fear that I
couldn't comfortably use Ghost as my backup program.

Louise
 

louise

Distinguished
Jan 24, 2003
343
0
18,780
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com says...
>
> "Louise" <none@nospam.com> wrote in message
> news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
> > I've just purchased Ghost 9. My plan was to do a full image
> > periodically and in between, do incremental backups - to a USB hard
> > drive. Running Win XP Pro.
> >
> > The full image is working fine.
> >
> > I want to be able to do incremental backups when I want to - when I'm
> > not using my computer - NOT on a schedule because my usage times are
> > erratic and a scheduled backup, no matter when I set it for, will
> > interrupt me - I want to do manual incremental backups every day.
> >
> > I've searched the help files and it looks to me like I can do a manual
> > image when I want to, but incrementals have to be scheduled.
>
> No they dont, its just poor documentation.
>
> Just set it up as you are told to and it should be obvious how to
> do the incremental backups manually once you have done that.
>
> Once you have setup the backup job, in the advanced view,
> just select the Backup Jobs tab and see that job listed as
> unsheduled. There will be a 'run job now' entry in the
> Backup Job Tasks list on the left when you have the job selected.
>
> > Is there any way around this
>
> Yep, its trivial to do in practice.
>
> > or have I missed something?
>
> The documentation has basically.
>
>
>
Ghost seems to "know" that when I hit the run backup option, it will do
an incremental backup. How does it know when it's time to do another
full image?

Thanks.

Louise
 
G

Guest

Guest
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

On Tue, 11 Jan 2005 16:30:22 -0500, Louise <none@nospam.com> wrote:

>Ghost seems to "know" that when I hit the run backup option, it will do
>an incremental backup. How does it know when it's time to do another
>full image?

I know this isn't what you asked, but True Image is pretty good at
this. Once you've scripted various backups with the wizard (full,
incremental, different source/destination drives, whatever), you can
have it do any of them; just select the one you want and tell it to
run now.

I only tried Ghost 8 briefly, because it just wasn't user friendly and
I don't have the time to diddle with cantankerous software. Haven't
tried Ghost 9 because TI is working well for me.


--
Neil Maxwell - I don't speak for my employer
 
G

Guest

Guest
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

"Louise" <none@nospam.com> wrote in message
news:MPG.1c4e0f764ee225d698975f@news.newsguy.com...
> In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com says...
>>
>> "Louise" <none@nospam.com> wrote in message
>> news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
>> > I've just purchased Ghost 9. My plan was to do a full image
>> > periodically and in between, do incremental backups - to a USB hard
>> > drive. Running Win XP Pro.
>> >
>> > The full image is working fine.
>> >
>> > I want to be able to do incremental backups when I want to - when I'm
>> > not using my computer - NOT on a schedule because my usage times are
>> > erratic and a scheduled backup, no matter when I set it for, will
>> > interrupt me - I want to do manual incremental backups every day.
>> >
>> > I've searched the help files and it looks to me like I can do a manual
>> > image when I want to, but incrementals have to be scheduled.
>>
>> No they dont, its just poor documentation.
>>
>> Just set it up as you are told to and it should be obvious how to
>> do the incremental backups manually once you have done that.
>>
>> Once you have setup the backup job, in the advanced view,
>> just select the Backup Jobs tab and see that job listed as
>> unsheduled. There will be a 'run job now' entry in the
>> Backup Job Tasks list on the left when you have the job selected.
>>
>> > Is there any way around this
>>
>> Yep, its trivial to do in practice.
>>
>> > or have I missed something?
>>
>> The documentation has basically.
>>
>>
>>
> Ghost seems to "know" that when I hit the run backup option, it will do
> an incremental backup. How does it know when it's time to do another
> full image?

It keeps a full track of what backups were done and can work it out from that.
 
G

Guest

Guest
Archived from groups: comp.sys.ibm.pc.hardware.storage (More info?)

and how does one alter the Data Execution Prevention (DEP) policy to allow
Norton Ghost 9.0 to launch its services during startup??

Cheers


"Sam" <scams@msn.com> wrote in message
news:34jb2hF4c1abjU1@individual.net...
> Don't know if your problem with XP SP2 was because of the following, but
> will quote part of the applicable Ghost document just in case. Sam
>
> Document ID:2004101410380862
> Last Modified:12/20/2004
>
>
> Norton Ghost 9.0 compatibility with Windows XP Service Pack 2
> Situation:
> You need to know if Norton Ghost 9.0 is compatible with Windows XP Service
> Pack 2.
>
> Solution:
> Norton Ghost 9.0 is compatible with Windows XP Service Pack 2. However,
> you need to modify the Data Execution Prevention (DEP) policy to allow
> Norton Ghost 9.0 to launch its services during startup.
>
> If you have already installed Ghost 9.0 and Windows XP Service Pack 2, see
> the document Blue screen error after installing Norton Ghost 9.0 or
> Windows XP Service Pack 2
>
>
>
>
>
>
> "Irwin" <ebct@hotmail.com> wrote in message
> news:1105481451.932965.321610@f14g2000cwb.googlegroups.com...
>> Just yesterday, I gave up on Ghost 9. Too buggy for my taste. Others
>> have made similar comments. Perhaps with work it will function
>> consistently, but why put so much work into it when Drive Image 2002
>> and Ghost 2003 work so well. I installed Ghost 9 onto a fairly new
>> install of XP SP2, and it hangs, crashes, and fails to liveupdate. So,
>> I'm giving up for now, and going back to the tried and true by putting
>> DI 2002 back on.
>>
>> I have Drive Image 7 laying around, maybe it will work better even
>> though Ghost 9 and DI 7 are similar programs.
>>
>> Irwin
>>
>> Louise wrote:
>>> In article <34isduF4706oaU1@individual.net>, rod_speed@yahoo.com
>> says...
>>> >
>>> > "Louise" <none@nospam.com> wrote in message
>>> > news:MPG.1c4d187b2b4acaea9897bc@news-server.nyc.rr.com...
>>> > > I've just purchased Ghost 9. My plan was to do a full image
>>> > > periodically and in between, do incremental backups - to a USB
>> hard
>>> > > drive. Running Win XP Pro.
>>> > >
>>> > > The full image is working fine.
>>> > >
>>> > > I want to be able to do incremental backups when I want to - when
>> I'm
>>> > > not using my computer - NOT on a schedule because my usage times
>> are
>>> > > erratic and a scheduled backup, no matter when I set it for, will
>>> > > interrupt me - I want to do manual incremental backups every day.
>>> > >
>>> > > I've searched the help files and it looks to me like I can do a
>> manual
>>> > > image when I want to, but incrementals have to be scheduled.
>>> >
>>> > No they dont, its just poor documentation.
>>> >
>>> > Just set it up as you are told to and it should be obvious how to
>>> > do the incremental backups manually once you have done that.
>>> >
>>> > Once you have setup the backup job, in the advanced view,
>>> > just select the Backup Jobs tab and see that job listed as
>>> > unsheduled. There will be a 'run job now' entry in the
>>> > Backup Job Tasks list on the left when you have the job selected.
>>> >
>>> > > Is there any way around this
>>> >
>>> > Yep, its trivial to do in practice.
>>> >
>>> > > or have I missed something?
>>> >
>>> > The documentation has basically.
>>> >
>>> >
>>> >
>>> Ghost seems to "know" that when I hit the run backup option, it will
>> do
>>> an incremental backup. How does it know when it's time to do another
>>> full image?
>>>
>>> Thanks.
>>>
>>> Louise
>>
>
>