Nvidia's H100 AI GPU shortages ease as lead times drop from up to four months to 8-12 weeks

Nvidia H100 NVL dual GPU PCIe solution
(Image credit: Nvidia)

According to Digitimes, Dell Taiwan General Manager Terence Liao reports that the delivery lead times of Nvidia H100 AI GPUs have been reduced over the past few months from 3-4 months, as we previously reported, down to just 2-3 months (8-12 weeks). Server ODMs revealed that supply is finally easing up compared to 2023 when it was virtually impossible to attain Nvidia's H100 GPUs.

Despite decreasing lead times, Liao states that demand for AI-capable hardware is still extremely high. Specifically, AI server purchases are supplanting general-purpose server purchases in businesses, even though AI servers are incredibly costly. However, he believes that procurement time is the only reason for this.